Zimbabwe is set to clear its arrears with Mozambique and
South Africa after securing a US$100 million facility from Afreximbank and
revive a 30-year trilateral agreement with the two neighbouring countries as
part of immediate-term solutions to stabilise local power supplies.
The trilateral agreement signed in 1990 allows Zimbabwe to
negotiate for “firm and competitively priced” electricity from Cahora Bassa and
Eskom, while paying off arrears is expected to unlock 550 megawatts (MW) from
the regional utilities.
The Sunday Mail understands that President Emmerson
Mnangagwa discussed the matter with his Mozambican counterpart, President
Filipe Nyusi, during his visit to Maputo a fortnight ago.
Government has prioritised establishing stable power
supplies to drive economic growth.
Separately, the Zimbabwe Electricity Supply Authority
(Zesa) has already paid two European companies to restore two units at Hwange
Thermal Power Station — units three and six — by March this year.
Zesa executive board chairperson, Dr Sydney Gata, was
bullish that the country would experience relatively milder load-shedding than
last year.
“Frankly speaking, we should not have had the severe
load-shedding that we experienced last year. Zesa and the past ministry failed
to renew a primary agreement that was due for renewal in 2012. This trilateral
agreement provides Zimbabwe first right of refusal to import 500MW of firm
power at a very competitive tariff from Cahora Bassa,” said Dr Gata.
“This agreement was a result of the Mozambique government
assisting us to access what was South Africa’s share of Cahora Bassa, at a time
when SA also had a surplus. So with considerable support from Mozambique’s
government, SA surrendered 500MW of its entitlement to Zimbabwe for which we
were to build the Bindura-Cahora Bassa lines, also called the Bindura-Songo
lines, which would reach to Dema substation.”
The agreement reportedly expired in 2012 but was not
renewed. Government is presently renewing it.
Two units at Hwange, which have been down for a number of
years, are expected to be up and running by March, adding 300MW to the grid.
Two foreign companies are currently working to revive the
plants.
Dr Gata said: “We have been able to pay in advance to the
French and Italian companies, who are the original suppliers, for the overhaul
maintenance of the two units and it should be completed by mid-March. This
means that we will add another 300MW or so.”
Dr Gata added that the country could secure more power from
regional utilities once it cleared its arrears.
He, however, noted that although a US$100 million facility
had been secured from Afreximbank, there were delays in processing the
transaction owing to the December holidays.
“The second unfortunate thing is that while Zesa has raised
through a bank US$100 million to pay for arrears to Eskom; Electricidade de Moçambique
(EDM), which is the power utility for Mozambique; and Cahora Bassa, which is
like the ZPC (Zimbabwe Power Company) of Mozambique, there has been an
inordinate delay in procuring borrowing certificates and guarantees from
Government. It took almost two months to get the certificate.
“By the time they were issued just before Christmas,
everybody had gone on holiday and we were not able to process. As people come
back from the holiday, we are pursuing with the bank to clear the arrears and
activate support of up to 400MW from Eskom and 150MW from EDM.”
Overall, the country’s debt to the regional utilities
initially stood at US$70 million. “In respect of Cahora Bassa, it is both to pay for the
arrears and also renegotiate an extension of the old agreement.
“In respect of Eskom, the condition precedent is to pay for
the arrears. With EDM it is also to pay for the arrears.”
As part of efforts to improve Zesa’s efficiency, the
parastatal would be restructured by mid-March through a rebundling process.
“I have set up a board committee for the rebundling but it
is a fairly easy exercise to undertake with respect to policy and structure
because the Government has decided what it wants to do. We may appoint a
consultant to help us with the structure.
“In my case, I was the person appointed to establish the
old Zesa in 1986, in January, when I was given the assignment to amalgamate the
six units that existed then,” said Dr Gata.
The subsequent structure that was assumed by the local
power utility then, Dr Gata added, was similar to that of the Central
Electricity Generating Board of the United Kingdom.
He said retrenchments were “unavoidable at the top” as a
result of the ongoing exercise. The majority of middle managers and other staff
will be spared.
In a separate interview, Energy and Power Development
Minister, Fortune Chasi, confirmed a major shake-up was looming at Zesa.
Speaking after a meeting with leaders of the Energy Sector
Workers Union of Zimbabwe in Harare, Minister Chasi said disciplinary action
had commenced against those involved in shady dealings at the power utility.
“We have already started implementation of the contents and
recommendations of the forensic audit, key of which is disciplinary hearings
around individuals who may have been involved in any acts of misconduct that
have caused loss to Zesa.
“I want to assure you that anyone who deprived Zesa in an
illegal way, the law will catch up with them.” He said the forensic audit will
be presented before Parliament soon.
Government would not tolerate a perfunctory approach to
work by Zesa workers, he said.
“I was briefed of incidents where we had managers who had
the arrogance to tell consumers that they would not switch on power or fix
faults. We have these reports and we will take appropriate action.” Sunday Mail